Construction Timing / Phases

SEV BIA representatives are meeting with senior management from the City, TTC and Metrolinx and hope our efforts with these decision-makers will help to ensure that the LRT is properly planned and construction will be completed with minimum disruption to the residents, traffic flows and businesses along the Sheppard corridor.

McCowan to Markham                        October 2009 to December 2010

Midland to McCowan                          March 2011 to December 2011

LRT construction information in this news posting was obtained from TTC officials – and is subject to changes in the final TTC plan that will be approved by City Council.


Back to News

Welcome to SEVBIA.com Log In
Find a Business

news

Construction Timing / Phases

SEV BIA representatives are meeting with senior management from the City, TTC and Metrolinx and hope our efforts with... More

Vehicle Turn Signals in SEV BIA

The LRT will run down the middle of a widened Sheppard Avenue.... More

Sheppard East LRT Plan

Sheppard East Village continues to be served by good TTC bus service on five major roads – Midland, Brimley, McCowan,... More

SEV BIA meets with TTC about LRT

TTC officials met recently with the Sheppard East Village board to discuss their plans and to obtain our input about... More